Power and Renewables

Transmission Projects Advance in New York and New England

byAdam Jordan

The Northeastern U.S. has some of the most ambitious decarbonization goals in the nation, and some of the most vocal detractors to new infrastructure. This is notable when any project advances, let alone begins construction, as in the case of the Champlain Hudson Power Express (CHPE) HVDC line. Meanwhile, a project in Maine is in the early stages, but its advancement starts to hint at costs and challenges coming down the pike.

Of course, these are just two projects of note. Look for continuing research from Enverus’ experts as more milestones are reached. The first quarter of 2023 will be exciting with the launch of 90-day forecasts for both NYISO and ISO-NE. These projects are well beyond 90 days out, but what we study today will help us understand what happens in the future.

Now, let’s take a further look at these two transmission projects.

New York

The CHPE is a planned 339-mile HVDC transmission project designed to move clean, hydro power from Quebec to New York. The project’s capacity is listed as 1,250 megawatts and it will blend submarine and terrestrial elements, snaking under Lake Champlain and through the Hudson River Valley.

The project announced financial close Nov. 1 and has since ceremonially broken ground and started the construction phase.  The project will run from an existing HVAC converter at the Hertel substation outside Montreal, to the Canada-U.S. border at Riviere Richelieu. Hydro Quebec will be responsible for all construction on the Canadian side of the border. The terminus of the project is in Astoria, Queens in New York. While the project is scheduled to finish construction in 2026, it’s not too early to begin evaluating the impact.

What happens when you inject 1,250 megawatts of power into the existing 345 kilovolt system in Astoria? Astoria is a complex area, and many projects in the interconnection queue plan on connecting in the Astoria area or within Queens County, New York. Enverus data show more than 1,200 megawatts of energy storage projects are at some phase of development in the immediate vicinity of the Astoria Annex 345 kilovolt substation, where CHPE will connect.

New York map showing transmission by voltage and power plants by project type
Source: Enverus PRISM.

There are also some large wind projects slated to connect in the vicinity, and Clean Path New York is planning to connect to the grid just south of Astoria, at the Rainey substation.

Injecting what amounts to gigawatts in the Astoria area will create and exacerbate local congestion. Two constraints jump to immediate attention: ASTANNEX 138 ASTORIAE 138 1 and ASTANNEX 345 E13THSTA 345 1, with the Astoria-Hellgate basket of constraints also showing higher flows. The energy storage projects, to the extent they are completed, will provide some balancing support for congestion and energy cost during peak hours, but with short discharge durations, they aren’t expected to overshadow the influx of power.

The increase in congestion will start to drive more basis between Zone J and update regions with the J/K spread also taking a jump, all else being equal. But all else is not equal, given the projects in the works. Offshore wind coming online in New York, New Jersey and New England, will play an important role in the market landscape by the time CHPE is energized.

New England

There are two projects taking a step forward in Maine. State regulators granted initial approval for a transmission line and wind farm located in Aroostook County in Northeast Maine. Both projects have some hurdles to clear, including how much ratepayers will contribute to each project.

LS Power’s bid won approval for a 345 kilovolt transmission line that would connect a portion of wind-rich, rural Maine to the rest of the New England system. Currently, there is a small pocket of Maine that lies outside of ISO-NE, connected to New Brunswick. The proposed line would allow for delivery of the planned wind farm’s energy directly into New England instead of flowing into Canada, where it may or may not flow back into the states via existing interfaces.

The following image shows existing 345 kilovolt infrastructure and proposed transmission additions in green. Note, the path has not been finalized for the northern branch. In this case, crossing critical habitat (Canadian lynx and Atlantic salmon) is not viewed as insurmountable. Proposed projects are also shown in the image. Other planned projects are in western and southern areas where existing infrastructure makes connection more attractive.

Enverus Blog New Hampshire map showing transmission by voltage, power plants by project type and critical habitat by common name
Source: Enverus PRISM.

The wind farm, a 1,000-megawatt plant named King Pine, has been awarded to Longroad Energy. It stands to reason that the fate of the wind farm is dependent on the completion of the transmission project, although that is not explicitly stated based on research.

Putting aside any doubt that these projects will be completed, how will these projects change the landscape? Congestion is already common when there is strong wind in Maine. The transmission and wind projects are sized in relation to the other to an extent. A 1,000 megawatt wind farm connected to a 345 kilovolt line around 100 miles long would almost fully utilize the line’s capacity. The doubling of a circuit between Cooper’s Mill and Maine Yankee substations hints at the underlying engineering and subsequent impact. While power will move somewhat unimpeded to the area south of Augusta, it will eventually reach a bottleneck flowing further south into New Hampshire and Massachusetts. The further downstate the congestion occurs, the more impactful it will be on the Maine Zonal price. While current wind driven constraints are moderately bearish on Maine, the new additions are viewed as being high impact. Zonal basis between Maine and Massachusetts will increase upon completion of these projects.

The projects in New York and Maine are quite different but do underscore the need and willingness to pay to improve system reliability while marching toward a lower carbon future. New York and New England have little to no dispatchable generation in their planning queues — it’s predominantly wind, solar and short duration batteries. Maine, New Hampshire and Vermont all have a history of being unfriendly to transmission projects. Will the LS Power project fare different?

Transmission is an effective way to tap existing hydro power in Quebec and allow for the build out of wind in rural areas. With another winter in full swing and ever-increasing competition for natural gas, will the public open their mind to transmission? Hopefully it won’t take a catastrophe to turn public opinion, but time will tell.

Picture of Adam Jordan

Adam Jordan

Adam brings more than 15 years of power market experience to Enverus. His expertise aids all stakeholders in the power space through the energy transition. Prior to joining Enverus, Adam led a research team covering the seven deregulated U.S. power markets. Adam has also worked for Independent Power Producers as an analyst, getting hands on with operations, hedging and planning activities. He holds a degree in Economics & Finance from Bentley University.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Enverus Press Release - Utica oil: America’s modest middleweight contender
Publications
ByJoseph Gyure, Editor, Enverus Intelligence®

U.S. drilling day rates took a tumble in 2024, finishing the year lower than they began for the first time since the COVID-19 pandemic. The Enverus Day Rate Survey’s U.S. composite day rate declined for the 11th consecutive month to...

Oil-drilling-officeworker-energy
Publications
ByMatthew Keillor, Editor, Enverus Intelligence®

Operators have little incentive to increase Haynesville production until gas prices increase, but higher demand is on the way for LNG and electricity generation.

Download our free e-book to explore key insights and strategies for navigating volatility in U.S. power trading markets.
Energy Transition
ByMarc De Guzman

Interconnection queue durations across independent system operators (ISOs) have lengthened and the proportion of projects successfully reaching completion is shrinking. To explore this in detail, Enverus Intelligence® Research captures the average duration of each phase in a project’s lifecycle, the...

Enverus Press Release - Blue hydrogen: Greening the bottom line
Energy Transition
ByAlex Nevokshonoff, Enverus Intelligence® | Research (EIR) Contributor

The finalized 45V clean hydrogen production tax credit provides clarity and incremental flexibility for electrolytic (green) and methane-derived (blue) hydrogen developers but may still fall short of revitalizing the industry. The latest rules allow electrolytic producers to utilize retiring nuclear...

power-grid-congestion-3
Power and Renewables
ByCarla Rodriguez

Explore how SPP Markets+ in 2027 aims to enhance grid reliability, renewable integration, and market efficiency across the Western U.S. through innovative collaboration.

affordable energy
Energy Transition
ByAmyra Mardhani

Mergers and acquisitions in the energy and power sector reached $129 billion in the first three quarters of this year, up from $120 billion in the same period last year, despite a slowdown in the third quarter. Valuations are stabilizing...

Enverus Press Release - Enverus Integrates With Fendahl to Enhance Energy Trading and Risk Management Solutions
Energy Transition
ByBrynna Foley

To mark the close of 2024, Enverus Intelligence Research® created a roadmap to the 2025 energy transition landscape, covering power, subsurface, low-carbon fuels and energy transition investment. As the industry continues to evolve, we find these key themes emerging in...

energy-transition
Energy Transition
ByAmyra Mardhani

TRACKING THE ENERGY TRANSITION MARKET | Nuclear, IPPs Soar; Solar Installers Hit by Policy Risks

data-center-demand
Power and Renewables
ByRobin Grathwohl

Discover how to site data centers effectively during the clean energy transition. Learn about renewable energy integration, reliable power sources, land suitability and cost-effective strategies with insights from Enverus PRISM®.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert